'Issues' Over New Flood Defence Plan

Summary


RE-SUBMITTED plans for the Pounds 8.5million flood defence scheme around Shaldon have been recommended for approval.

The scheme, put forward by the Environment Agency, includes the raising of 940 metres of existing foreshore wall, the reconstruction of 340 metres of existing wall and the construction of 130 metres of new wall.

See the full content of this document

Extract


'Issues' Over New Flood Defence Plan

Plans also include eight flood gates which will close when there is a flood warning; surface water drainage wor...